Phase 4 Project Update

A contract has been fully executed with the state to complete this project.  Permits are still pending.  It is anticipated that the active project beach fill construction related to the state grant will occur on November 16, 2023, as allowed by permit.  Stockpiling of beach compatible material and other mobilization items will begin this Spring. Once active beach fill construction begins on November 16, 2023, Based on permitting and production rates, the project is anticipated to be complete by April 30, 2024.